Research, analysis, and perspectives on the built world.
Six U.S. grid operators filed large-load reforms at FERC between 13 and 20 November 2026. POWER reports they generally use a 50 MW threshold, but they differ on non-firm service, bring-your-own-capacity rules and upgrade costs. This guide compares the plans, the curtailment prices and the requested effective dates.
November 24, 2026 ·7 min read
Accelerated infrastructure development means one accountable team runs site selection, power validation, diligence, design and permitting in parallel, so a project such as a data center reaches shovel-ready sooner. The time saved comes before construction. This guide defines the term and shows how it works for data centers. It also explains how accelerated development differs from modular construction, which speeds up the build rather than the work before it.
November 24, 2026 ·5 min read
Hourly matching means covering a data center's power use in every hour with clean power generated in that same hour, not just over a year. Spain now requires 80% hourly matching for data centers of 10 MW or more, and EU and U.S. hydrogen rules move to hourly matching in 2030. Here is how it works and why it changes site selection.
November 24, 2026 ·6 min read
Georgia's 100 MW data center rule is a Public Service Commission rule for Georgia Power, approved in January 2025. It allows 5 to 15 year contracts, minimum billing and upstream cost responsibility for new customers above 100 MW, and new contracts go to the PSC for review. It is not a new state statute.
November 23, 2026 ·5 min read
TVA's Capacity Commitment Charge applies to new and expanding data center loads above 5 MW. Its first agreement, signed 10 November 2026, totals $1.7 billion: $31 million at signing and 59 installments, at approximately $1.5 million per MW of requested capacity above 5 MW. TVA says the rate may be revised for future cohorts.
November 23, 2026 ·5 min read
There is no single national definition of a large load. Six grid operators filed reforms at FERC in November 2026 that appear to accept a 50 MW threshold, while TVA uses above 5 MW, the DOE proposal pointed to above 20 MW and Georgia Power's rule starts above 100 MW. The filings are proposals, and the service offered after the threshold differs by region.
November 23, 2026 ·5 min read
Size a data center transformer from the design load: convert MW to MVA using power factor, apply the redundancy design, add growth, and confirm the rating with the utility and the engineer of record. Wood Mackenzie reported 162-week transformer waitlists in October 2026, so order only against a frozen design.
November 23, 2026 ·5 min read
An interconnection readiness deposit is at-risk money that shows a project is ready before a grid operator studies it. PJM's 16 November 2026 Fast Energization filing proposes stricter readiness requirements applied earlier, with deposits posted at application and a cost recovery agreement required for large loads. It is a proposal, not a rule.
November 23, 2026 ·5 min read
Giga Energy says its 60 MW Project Clay in Hunt County, Texas, leased for 10 years, will be built in under eight months. The speed comes from decisions made before construction: power, design basis, cooling and procurement.
November 20, 2026 ·6 min read