A new type of firm: Build partners with
Index.to accelerate institutional development with AI. Learn More
Research, analysis, and perspectives on the built world.
FERC's June 2026 action on Docket RM26-4-000 establishes the first national framework governing how large electrical loads above 20 MW connect to the U.S. interstate transmission system. This piece explains what the rule requires, who it hits first, and the five actions data center developers should take before the compliance period closes.
June 22, 2026 ·5 min read
Power transformer lead times from major manufacturers have reached 48-60 months in 2026, with Tier 1 suppliers booked through 2030. This post explains the five-stage electrical procurement workflow that works in today's market, from pre-LOI utility confirmation through continuous schedule monitoring, and the budget implications developers must model now.
June 22, 2026 ·5 min read
Training and inference AI workloads require fundamentally different data center designs: site selection logic, cooling architecture, electrical infrastructure, and underwriting frameworks diverge at nearly every level. This explainer maps those differences and explains why a mixed-design compromise serves neither workload well.
June 22, 2026 ·5 min read
A deficient grounding and bonding system in a data center causes equipment failures, EMI interference, and safety risks that are difficult and expensive to correct after energization. This guide covers the three layers of a data center grounding system, separately derived system requirements, lightning protection coordination, and what developers should verify in design review.
June 21, 2026 ·5 min read
Commissioning punch lists on large data center projects generate hundreds to thousands of items across mechanical, electrical, controls, and fire protection scopes. This post explains how AI can automate capture, deduplication, tracking, and documentation completeness while identifying where human engineering judgment is required for closure decisions.
June 21, 2026 ·5 min read
The choice between raised access floors and concrete slab construction shapes cooling architecture, structural capacity, and operational flexibility for the life of a data center. This guide explains when slab-on-grade is the right default for AI-era high-density builds and when raised floors remain a legitimate choice for specific applications.
June 21, 2026 ·5 min read
The Aligned Data Centers $40B acquisition by a Microsoft-Nvidia-BlackRock consortium marks a structural shift: hyperscalers are now taking equity in infrastructure platforms, not just signing leases. This piece explains what the $280B capex surge and rising hyperscaler M&A means for independent developers -- from valuation compression among mid-tier operators to the underwriting changes required to compete for premium exits.
June 19, 2026 ·7 min read
FERC will issue the first standardized national framework for large-load interconnection before June 30, 2026, covering any data center project above 20 MW connecting to interstate transmission. This piece explains what the rule is expected to contain -- 100% caused-cost assignment, curtailability options, hybrid facility treatment -- and the five actions developers should take before the order changes the baseline.
June 19, 2026 ·6 min read
Power purchase agreements now determine whether a data center project can be financed at all. This piece explains the three PPA structures (physical, virtual, utility service), why nuclear has become the preferred baseline for hyperscale power, the key PPA terms that drive construction financing, and where AI compresses the diligence and monitoring workflow without replacing the negotiation.
June 19, 2026 ·7 min read