Research, analysis, and perspectives on the built world.
There is no single acres-per-megawatt number for data centers. Land need depends on IT load, rack density, building height, substation, generator and cooling yards, setbacks, and stormwater rules. This guide defines net developable acreage, lists what takes up land on a campus, and gives a seven-step sizing method with an illustrative worked example and decision rules.
November 5, 2026 ·5 min read
A fiber lateral connects an existing fiber route into a data center site. Distance to a usable splice point, construction method, crossings, easements, and the need for diverse paths drive its cost and timeline. Validate lateral options with providers before LOI and time them to power delivery.
November 3, 2026 ·5 min read
Rank a data center site shortlist by removing sites that fail gating tests, scoring the rest on weighted criteria led by deliverable power, and applying tie-break rules. This guide includes an example scoring table, what evidence each rank needs, and common ranking mistakes.
November 2, 2026 ·5 min read
Retired coal plant data centers are becoming a serious siting strategy because they may offer land, transmission infrastructure and industrial zoning in one package. This post breaks down the site criteria developers need to underwrite, including switchyard reuse, environmental remediation, water, gas, demolition and community acceptance.
September 25, 2026 ·5 min read
Data center fire suppression is a room-level design choice that affects code, insurance, downtime and handover. This piece breaks down what NFPA 75 and FM Global actually require and where clean agent, pre-action and hybrid systems fit.
June 28, 2026 ·4 min read
A practitioner guide to dry utility coordination for data center development. Covers electrical service coordination (load studies, utility service agreements, transformer placement), fiber and telecom redundancy, duct bank and handhole design, and the six most common developer oversights that cause schedule slippage and cost overruns.
June 27, 2026 ·5 min read
AI-era data centers require fundamentally different generator fleet sizing -- Amazon runs 93 generators at 2.5MW each for a single site. This post explains the current methodology: how to calculate fleet size, why transient AI loads matter, fuel logistics at scale, and the regulatory constraints (Illinois Tier 4, Virginia NOx) shaping procurement decisions in 2026.
June 26, 2026 ·5 min read
Nuclear adjacency has moved from a secondary consideration to an explicit site screening criterion for data center developers in 2026. This post covers the five dimensions of nuclear-adjacent evaluation, the FERC colocation framework, and AI's role in screening -- alongside what still requires direct relationships and engineering judgment.
June 24, 2026 ·5 min read
North American colocation vacancy hit 0.3% in Northern Virginia and 1% in Atlanta in Q1 2026, with 73% of the pipeline preleased before completion. This post explains how those market conditions change colocation underwriting, how colo and hyperscale development differ in practice, and where developers are finding viable opportunity in a supply-constrained market.
June 23, 2026 ·4 min read