Insights

Research, analysis, and perspectives on the built world.

Industry

How US Chip Curbs Are Hitting Data Center Loans

New US chip rules have lenders pausing data center and GPU loans. What changed on 19 November 2026 and what developers should now add to due diligence.

November 27, 2026

Workflows

What Is a Pre-Application Meeting for a Data Center?

A pre-application meeting maps a data center's permit path before any filing. What happens, what to bring, and a live example from San Diego County.

November 27, 2026 ·4 min read

Industry

Can a State Override a Local Data Center Vote?

Sometimes. Local governments usually control zoning for a data center building, but a state agency may permit the power plant or transmission that serves it. In November 2026 the Ohio Power Siting Board approved an up-to-800 MW behind-the-meter gas plant for a planned data center about two weeks after 81% of Ashville voters rejected the local agreement. This explainer covers what happened, why the state could decide, and how developers should map entitlement risk by agency.

November 26, 2026 ·5 min read

Industry

What Is Contribution in Aid of Construction (CIAC)?

Contribution in aid of construction (CIAC) is money a customer pays a utility to cover facilities the utility builds and owns to serve that customer. It is one of the main ways large loads such as data centers pay for the grid buildout they trigger. This explainer covers how CIAC works, Cheyenne Light's November 2026 FERC filing of three Microsoft agreements funded through CIAC, and what developers should check in a CIAC agreement.

November 26, 2026 ·5 min read

Workflows

What Is Construction Due Diligence?

Construction due diligence reviews a project's design, budget, schedule, contracts, team and site conditions before money is committed to building it. It differs from real estate due diligence, which tests whether the site supports the project at all. This guide covers what construction due diligence reviews, when it happens, and what changes on data center projects, where the power date and long-lead electrical equipment set the schedule.

November 26, 2026 ·5 min read

Industry

What Is ERCOT Batch Zero? The Dec 10 Audit Explained

Batch Zero is ERCOT's one-time study of large loads of 75 MW or more under PGRR 145. ERCOT has paused energization of new data centers and crypto facilities at that size until it files eligibility and community-impact reports with the PUCT on 10 December 2026. This explainer covers what Batch Zero is, what ERCOT is checking and what developers should do before those reports land.

November 25, 2026 ·6 min read

Technology

What Is MEP Design for an AI Data Center?

MEP design for an AI data center is the coordinated mechanical, electrical and plumbing design that turns a stated critical IT load into systems a utility, a tenant and a contractor can rely on. This explainer covers what each discipline includes, why AI campuses change the order of work, what a complete package contains and how Build runs it as part of one development program.

November 25, 2026 ·5 min read

Technology

Critical IT Load vs Utility Load: What's the Difference?

Critical IT load is the power available to computing equipment. Utility load is what the whole data center draws, including cooling, conversion losses and building systems. Leases are usually written on the first number; interconnection requests and large-load rules use the second. This guide explains the difference, how PUE connects the two, and how to use both numbers in site selection.

November 25, 2026 ·5 min read

Industry

What Is Non-Firm Transmission Service for Data Centers?

Non-firm transmission service is grid service that can be curtailed, which may let a data center energize before all upgrades for firm service are built. In November 2026, MISO, ISO-NE, NYISO and SPP proposed price-based non-firm options for large loads at FERC, with curtailment triggers from $25/MWh to $250/MWh. This guide explains the difference, the proposals and what developers should underwrite before FERC acts.

November 25, 2026 ·6 min read

Industry

Spain's Data Center Decree: What Developers Must Prove

Spain's Royal Decree 1032/2026 requires data centers of 10 MW or more to match at least 80% of each hour's power use with renewables generated that hour, mostly from new plants, and to meet WUE 0.1 and PUE 1.25 caps. An optional five-year phase-in allows 60% then 70% in peak hours in exchange for priority disconnection.

November 24, 2026 ·8 min read