Insights

Research, analysis, and perspectives on the built world.

Workflows

Gas Pipeline Lateral Access for Data Center On-Site Power: What to Confirm Before You Count on It

A gas lateral connects a data center site to a transmission pipeline so on-site generation can run on firm gas. Before relying on it, confirm pipeline proximity, firm capacity, an acquirable route, and a gas flow date that beats your generation date.

November 10, 2026 ·6 min read

Technology

Wildfire Power Shutoff (PSPS) Exposure for Data Center Sites: How to Screen It

Public Safety Power Shutoffs let utilities de-energize lines during high wildfire risk. Data center PSPS exposure follows the serving circuit, not just the parcel, so screen feeds against fire risk maps, shutoff history, and backup fuel autonomy.

November 10, 2026 ·6 min read

Workflows

Military and Radar Siting Constraints for Data Centers: When DoD Review Applies

Data center sites near military installations, special use airspace, or radar can face height limits and mitigation requests. Screen proximity, inventory tall elements for FAA filings, and use the DoD Siting Clearinghouse for early informal review.

November 10, 2026 ·6 min read

Workflows

Multi-Parcel Land Assembly for Data Center Campuses: How to Control Land Without Getting Held Out

Large data center campuses often require assembling several parcels from different owners. This guide explains how to rank parcels by criticality, structure options and contingent closings, run diligence across the whole assemblage, and set decision rules for holdouts, so the site is controlled as one buildable campus rather than a collection of separate deals.

November 9, 2026 ·6 min read

Workflows

Natural Hazard Screening for Data Center Sites: Wildfire, Extreme Heat, Seismic and Wind

Natural hazards beyond flooding, including wildfire, extreme heat, seismic activity, high wind and tornadoes, affect data center design cost, insurability and uptime. This guide explains which hazards matter, which public data sources to use for a first screen, how each hazard changes the project, and the decision rules developers use to pass, price or reject a site before LOI.

November 9, 2026 ·6 min read

Workflows

FAA Airspace Screening for Data Center Sites: When Height Limits and Form 7460-1 Matter

Data center sites near airports, heliports or military training routes can face FAA notice requirements and height limits that affect building height, generator stacks, rooftop equipment and construction cranes. This guide explains when 14 CFR Part 77 notice applies, how to screen a parcel before LOI, and how to sequence Form 7460-1 filings so airspace never becomes a late schedule risk.

November 9, 2026 ·6 min read

Workflows

Heavy-Haul Route Surveys for Data Center Sites: Can the Transformer Actually Get There?

A heavy-haul route survey checks whether oversize equipment, such as large power transformers, can physically travel from a rail or port unload point to a data center site gate. It covers bridge ratings, clearances, turning radii, overhead lines, permits, and the final access road. Run it before site control hardens, because a site with confirmed power but an undeliverable route still misses its energization date.

November 6, 2026 ·6 min read

Markets

GPU Delivery Date vs. Energization Date: How Neocloud Teams Should Time a Site Commitment

A neocloud team should commit to a data center site only when the credible energization date falls inside the window of its GPU delivery schedule. Power that arrives early burns rent on an empty building. Power that arrives late leaves purchased hardware idle. Use the credible date, not the quoted one, and rank each date by the evidence behind it: utility letter type, study stage, equipment orders, and access and entitlement status.

November 6, 2026 ·6 min read

Technology

Interconnection Voltage for Data Centers: What 69 kV, 138 kV, and 230 kV Mean for a Site

Interconnection voltage is the voltage at which a data center connects to the utility grid. Lower voltage connects faster and costs less but caps how many megawatts a site can ever draw. Higher voltage supports larger campuses but usually means a customer-owned substation and a longer study and equipment timeline. Size the voltage to full buildout, not phase one, and confirm the exact line and substation, not just the voltage class.

November 6, 2026 ·6 min read