Contribution in aid of construction (CIAC) is money, or sometimes property, that a customer pays a utility to cover the cost of facilities the utility builds and then owns, such as new lines, substations or a service extension needed to serve that customer. For data centers, CIAC is one of the main ways a utility makes a large load pay for the grid buildout it triggers instead of spreading that cost across other customers. In November 2026, Cheyenne Light, Fuel and Power filed three agreements at FERC under which Microsoft will fund new distribution and transmission facilities for three Wyoming data center campuses through CIAC payments.
For developers, CIAC is a capital cost that lands early, often before construction starts, and its terms shape both the budget and the schedule.
How CIAC works
The customer pays, the utility owns. The customer funds the facilities, but the utility builds, owns and operates them as part of its system.
The cost stays out of rates. Because the customer has paid for the plant, the utility does not recover it from other customers. In its Wyoming filing, Cheyenne Light said that because of the CIAC payments the capital costs of the facilities will be booked at $0, as reported by Load Factor News.
Payments can be staged and trued up. Agreements can set a series of payments tied to construction, then adjust to actual cost. In a separate November 2026 Ohio filing, Google's share of an advanced conductor upgrade is to be trued up to actual cost through contributions in aid of construction paid with a tax gross-up, according to Pique's review of the PUCO application.
Other fees can sit alongside it. The Wyoming agreements also include a negotiated construction fee and an operation and maintenance fee, according to the same Load Factor News reading of the filing.
The Wyoming filing
What was filed: Cheyenne Light filed three Facility Expansion Agreements with Microsoft at FERC on November 24, 2026, in Docket ER27-634, covering the Meadowlark, Equality and Frontier campuses, with a requested effective date of December 24, 2026.
How Microsoft pays: Through contribution in aid of construction payments, Utility Dive reported on November 25.
Why it went to FERC: Cheyenne Light does not believe FERC has jurisdiction over these retail agreements, but filed them "out of an abundance of caution" given the agency's recent statements on cost recovery agreements for transmission costs caused by large loads, according to Utility Dive.
What is not public: The agreements are redacted, so payment amounts, load and schedule are not disclosed.
The filing also shows the policy direction. Utilities and regulators are looking for ways to make sure large loads, not existing customers, carry the cost of the grid they need. Utility Dive reports that Cheyenne Light also plans to serve data centers through a large power contract tariff and a proposed large customer transmission cost adjustment mechanism designed to insulate its other customers from those costs.
CIAC and other ways large loads pay
| Mechanism | What the customer pays for | When it is paid |
|---|---|---|
| Contribution in aid of construction | Facilities built to serve the customer, owned by the utility | Up front or in stages during construction |
| Large-load tariff terms | Minimum bills, demand charges and contract terms in exchange for service | Over the life of the service contract |
| Deposits and financial security | Collateral that the project will proceed and take service | At interconnection or contract milestones |
These often appear together. Our posts on large-load tariffs in underwriting, interconnection readiness deposits and what counts as a large load cover the other two.
What to check in a CIAC agreement
Which facilities are included, and which upgrades could be added later?
Is the amount a fixed price, an estimate with a true-up, or capped?
How do payment dates line up with your financing, land closing and energization date?
What happens to payments already made if the project is delayed, downsized or canceled?
Is there a tax gross-up, and how is it calculated?
Who carries cost overruns and schedule delays on the utility's side?
Why it matters at the site stage
CIAC can decide whether a site works. Two sites with similar power can carry very different upgrade bills, and the payment often comes due before any revenue. That is why we try to establish the likely scope and cost of utility-built facilities during site validation, not after land is under contract. Build is a vertically integrated development firm, and power validation is part of how our site selection service takes projects from site to shovel-ready.
Sources
Utility Dive: Bright Horizon utility lands Microsoft data center deals amid Wyoming buildout, November 25, 2026
FERC eLibrary: Cheyenne Light, Fuel and Power Company filing, Docket ER27-634, November 24, 2026
Load Factor News: Cheyenne Light files three Microsoft data center agreements at FERC, November 25, 2026
Pique: Google and Ohio Power seek approval to upgrade Columbus lines with advanced conductors, November 23, 2026