Short answer: Non-firm transmission service is grid service that can be curtailed or interrupted, instead of being reserved as firm capacity the operator will serve except in emergencies. For data centers, the practical difference is reliability and timing. Firm service usually waits for the network upgrades that make the load deliverable year-round. Non-firm or interim service can let a project energize earlier, or run part of its load on a flexible basis, if the tenant can accept interruptions or the site has backup generation. In November 2026, four U.S. regional grid operators proposed price-based non-firm options for large loads in filings at the Federal Energy Regulatory Commission (FERC). None of those proposals is in force until FERC approves them.
Firm vs non-firm, in plain terms
On the transmission system, firm service is reserved capacity with a high priority. Non-firm service is lower priority. The operator can reduce or stop withdrawals when the system is constrained, when a price threshold is hit, or when a manual instruction is issued, depending on the tariff.
That idea is not new. Open-access transmission tariffs have long included non-firm point-to-point service. What changed in November 2026 is that several regional operators proposed large-load products built around that flexibility, with explicit price triggers, eligibility rules and, in some cases, different capacity obligations.
For a data center, the underwriting questions are: how often could the load be curtailed, who gives the instruction, what backup sits behind the meter, and does the tenant's lease allow that operating mode?
What the November 2026 filings propose
Six regional operators filed large-load reforms at FERC between 13 and 20 November 2026: ISO New England, CAISO, MISO, NYISO, PJM (with a separate filing by PJM's transmission owners) and Southwest Power Pool (SPP). POWER magazine reports that they generally use a 50 MW threshold to identify a large load. Our comparison of the six grid operators' large-load plans covers the full set of differences. The non-firm service designs are one of the sharpest.
Four operators proposed price-based curtailment for large loads that take non-firm or comparable flexible service:
| Operator | Proposed service | When non-firm load is curtailed |
|---|---|---|
| MISO | Grid Responsive Integration Transmission Service (GRITS) | Locational price above $100/MWh, and during capacity advisories |
| ISO-NE | Interim and non-firm contract demand service | Redispatch above $250/MWh |
| NYISO | Non-firm withdrawal service, as part of its Large Load Integration Procedures | $200/MWh maximum bid price, plus operator-directed curtailment |
| SPP | Price Adaptive Load Service (PALS) | Dispatched to zero above a $25/MWh bid cap |
Source: POWER, drawing on the November 2026 FERC filings. ISO-NE said its $250/MWh price occurred in about 1% of hours from 2021 to 2025. MISO said historical data suggest its threshold would permit service in more than 95% of hours. Those figures are historical illustrations offered by the operators, not guarantees of future curtailment.
The price caps are not interchangeable. SPP's $25/MWh cap would interrupt PALS load far more often than ISO-NE's $250/MWh trigger would, if comparable prices appeared in both regions. A tenant that can shift or island some load may be able to use a tight cap. A tenant that needs unbroken IT service probably cannot, unless behind-the-meter generation or other backup can cover the curtailed megawatts. See also data center demand response.
MISO's GRITS proposal is a mix, not an all-or-nothing choice. POWER reports that MISO illustrates a 500 MW facility that elects 200 MW of firm service and up to 300 MW of non-firm GRITS demand. Firm GRITS demand would keep existing capacity obligations. Non-firm GRITS demand may be excluded from them.
SPP's PALS service, as proposed, would carry no additional resource adequacy obligation, and transmission charges would be assessed on actual hourly withdrawals at non-firm point-to-point rates, with a monthly cap tied to the customer's maximum hourly usage.
What about PJM and CAISO?
They filed in the same window, but their headline reforms are not the same price-cap products.
PJM proposed a Fast Energization Process that would combine generation interconnection and large-load transmission service studies in a single 12-month cycle. PJM's transmission owners also proposed a maximum rate for non-firm contract demand transmission service, based on the corresponding zonal firm rate and the zone's load factor. In one illustrative calculation reported by POWER, a firm rate of $90,000 per MW-year and a load factor of about 64.7% produced an annualized maximum non-firm rate of $58,219 per MW-year.
CAISO proposed a Flexible Interim Load Interconnection (FILI) arrangement to allow earlier energization subject to transmission constraints, and argued that a customer-specific generation procurement requirement is unnecessary under its existing resource adequacy framework.
Treat those as different tools: faster studies or interim interconnection in some regions, and ongoing price-responsive non-firm service in others.
When would this take effect?
Nothing in the November filings is effective until FERC acts. Requested dates differ by operator and, in several cases, by product. POWER reports that NYISO's Large Load Integration Procedures would take effect 1 February 2027, CAISO has requested 16 February 2027 for most reforms, most of PJM's transmission service revisions would take effect 16 March 2027, SPP has targeted PALS for the second quarter of 2028, ISO-NE would offer its new transmission services beginning 1 June 2028, and MISO does not anticipate implementing GRITS before 1 January 2029. All of those dates can move.
What developers should underwrite
Map the site to its operator and tariff. The service options, curtailment prices and capacity rules now differ by region. See what a large load is.
Decide whether any of the load can be non-firm. That is a tenant and design question, not only a transmission question. It affects MEP design, backup generation and lease terms.
Do not treat non-firm service as firm capacity. It can pull energization forward, or lower some charges, but it changes the operating case.
Watch FERC. These are proposals. Do not underwrite a 2026 site as if a 2028 or 2029 service already exists.
How Build helps
Build is a vertically integrated development firm. We use our own technology stack and proprietary data to take data center projects from site to shovel-ready, with one accountable team owning the outcome. We validate each site's power path against the utility and grid-operator rules that actually apply, including whether firm, interim or non-firm service is realistic for the tenant, and we carry the sites that pass through engineering to shovel-ready. See data center development and Build's services.
Key takeaways
Non-firm transmission service can be curtailed. Firm service has higher priority and usually waits for the upgrades that support it.
In November 2026, MISO, ISO-NE, NYISO and SPP proposed price-based non-firm options for large loads, with triggers ranging from $25/MWh (SPP) to $250/MWh (ISO-NE).
PJM and CAISO filed related reforms in the same window, focused more on faster or interim interconnection than on the same price-cap products.
None of the proposals is in force until FERC approves them, and several would not take effect before 2028 or 2029.
Non-firm service only helps a data center if the tenant and the backup design can accept the interruptions.