Sometimes, yes. In some states, local governments control zoning for a data center building, but a state agency holds the permit for the power plant, transmission line or other energy facility that serves it. When a project depends on that kind of facility, a local vote against the project does not necessarily stop the state permit. Ohio showed this in November 2026: the Ohio Power Siting Board approved an up-to-800 MW natural gas plant to serve a planned data center about two weeks after 81% of voters in the Village of Ashville rejected the local agreement behind the project.
For developers, the lesson is not that states will always overrule communities. It is that entitlement risk is split across agencies, and each piece of a campus can have a different decision-maker, timeline and appeal path.
What happened in Ashville, Ohio
April 2026: The Ashville Village Council approved a term summary with a data center developer covering two data center buildings and an associated natural gas plant that would serve them behind the meter. Residents gathered enough signatures to force a referendum on the council's resolution.
November 3, 2026: Voters repealed the resolution. The result was 1,469 votes against (81.61%) and 331 in favor (18.39%), according to Ballotpedia.
November 19, 2026: The Ohio Power Siting Board approved the 800 MW Ashville Energy Center on 110 acres in the village (case 26-196-EL-BGN). The plant will operate behind the meter to serve the adjacent data center and will not connect to the grid. The board adopted and modified an agreement among the developer's power affiliate, the Village of Ashville and board staff, with 41 conditions.
November 25, 2026: DCD reported that the board found the project met the statutory public interest requirement, pointing to economic benefits, the council's earlier backing and limits on construction noise. The board acknowledged the vote but said it holds the ultimate authority to issue the permit. Opponents have 30 days to ask for reconsideration, and an appeal to the Ohio Supreme Court could follow.
Why the state could decide
The vote and the permit were about different things. The referendum repealed a local resolution. The siting board ruled on a power generation facility, which is under its jurisdiction. In its own announcement, the board said it has jurisdiction over the generation facility but no authority over the approval of the data centers.
That split cuts both ways:
The state permit covers the power plant only. The data center buildings remain a local matter, so the practical effect of the vote depends on which local approvals the data center still needs.
The local vote does not cancel a state certificate. A project that has its generation permit can still face a fight over everything else on the site.
Rehearing and appeals add time. Even a granted state permit can stay open to challenge for months.
What this means for data center entitlement risk
Map who decides each piece. For each campus, list the building, on-site generation, substation and transmission, water and roads, and the agency that approves each one. A behind-the-meter plant can move part of the decision from the county or village to the state.
Treat a council vote as provisional. Where referendum rules allow, a council approval can be put to voters. Build the petition and election calendar into the schedule.
Do not confuse a permit with community acceptance. A state approval granted over local opposition can still bring appeals, political pressure and slower local decisions on the rest of the project.
Price on-site power as its own entitlement track. Generation brings its own permits, air and noise scrutiny, and a separate public process.
Our data center entitlement risk guide, by-right zoning vs special use permits and social license workflow go deeper on each step. For on-site generation, see behind-the-meter power for data centers.
Questions to ask on any candidate site
Which local approvals does the data center need, and can any of them be referred to voters?
If the project includes on-site generation or new transmission, which state agency permits it, and what is its review standard?
Has the community already voted on, or organized against, a similar project nearby?
What are the rehearing and appeal windows for each approval, and how do they affect the schedule?
How Build handles it
Build is a vertically integrated development firm. We use our own technology stack to find and validate sites and take them from site to shovel-ready, and entitlement is part of that validation from the start: who approves each piece of the project, under which rules, and how much community risk the site carries. See our site selection service and AI site selection for data centers.
Sources
Ohio Power Siting Board: OPSB authorizes new generation facilities in Fairfield and Pickaway counties, November 19, 2026
DCD: Ohio regulators approve up to 800MW gas plant set to power data center in Pickaway County, November 25, 2026
Ballotpedia: Ashville, Ohio, data center referendum (November 2026)