Short answer: An interconnection readiness deposit is money a developer puts at risk to prove a project is real before a grid operator spends study time on it. In its 16 November 2026 Fast Energization filing, PJM proposes to make readiness requirements stricter and to apply them earlier, with deposits posted in full at application and at risk at later decision points. Deposits are separate from study fees and from the eventual cost of network upgrades. For a large load, PJM also proposes that the customer enter a Transmission Owner Cost Recovery Agreement before it can join the process.
What is an interconnection readiness deposit?
A readiness deposit is a financial commitment that an applicant makes to stay in an interconnection or transmission service process. Its purpose is to filter out speculative requests. If a project drops out, some or all of the deposit can be lost or applied to network upgrades that other applicants now have to fund.
PJM says its Fast Energization proposal "moves readiness and financial requirements up to weed out speculative generation projects and Large Loads." PJM also says readiness requirements are "now stricter and applied earlier."
How would PJM's readiness deposits work?
The details come from the tariff text in PJM's 16 November 2026 filing in docket ER27-531. In the filing's structure:
| Stage | What happens to readiness deposits |
|---|---|
| Application | The first readiness deposit is due with the application |
| Decision Point I | A second readiness deposit stage, and deposited funds become at risk |
| Decision Point II | A third stage, with further funds committed and at risk |
| After the cycle | Remaining deposits are refunded, unless underfunded network upgrades need them |
The filing says deposit amounts are based on the project's MW size and, where applicable, the study results. It also says study deposits and readiness deposits are separate obligations that cannot be commingled or moved between requests.
How much would a readiness deposit cost?
We cannot give one number for large loads, and you should be cautious of anyone who does. The amounts depend on the tariff language and on the request size. Trade press covering PJM's October 2026 workshop draft reported a figure of $30,000 per MW at application, or $15 million for a 500 MW request. That was a draft, and we did not find that figure confirmed in the November tariff text we reviewed. Read the filing for the current terms before you budget.
What the filing does make clear is the direction: more money, posted sooner.
What happens to the deposit if a project withdraws?
According to the filing's tariff language, refunds depend on the study phase at which a project was withdrawn or terminated. When all requests in a cycle have signed final agreements or withdrawn, PJM identifies network upgrades that are underfunded because of withdrawals. Deposits are applied pro rata to those upgrades first, and if there are none, all readiness deposits are refunded. Remaining funds after upgrades are made whole are refunded pro rata.
In plain terms: a withdrawal can cost you money, and it can raise costs for others, which is why PJM wants the money at risk early.
What else does PJM want from a large load applicant?
The filing says Eligible Customers seeking transmission service on behalf of Large Loads must enter into a Transmission Owner Cost Recovery Agreement to enter the process. It also says physical changes to projects and load are not allowed after application, because they would change the dynamic models submitted. A developer who wants to change a project must withdraw and resubmit in the next cycle.
That means readiness is not only cash. It also means a settled design, a signed agreement with the transmission owner and a clear load profile at the time of application.
When would this apply?
Not yet. This is a proposal. PJM asked FERC for a 60-day comment period and an order within 120 days. Our explainer on PJM Fast Energization covers the 12-month cycle and the expected timeline. Until FERC acts, underwrite on the current process.
How should a developer prepare?
Lock the load profile. Changes after application mean withdrawing and resubmitting.
Get the transmission owner engaged early. A cost recovery agreement is a gate, not a formality.
Show site control. The process is built to favor projects that are ready to build.
Budget the deposit as at-risk capital. Treat it like earnest money that may not come back if the project exits.
Re-read the tariff at each stage. Amounts and refund rules can change as FERC reviews the filing.
What Build does here
Build is a vertically integrated development firm. With our own technology stack, we take data center projects from site to shovel-ready, so a project reaches an application with its load, power path and approvals settled. The client gets a package that is ready to meet the readiness gate, rather than finding the gaps after money is at risk.
Key takeaways
A readiness deposit is at-risk money that shows a project is ready, and PJM proposes to require more of it, sooner.
Deposits are separate from study fees and network upgrade costs.
Large load applicants would also need a Transmission Owner Cost Recovery Agreement.
Deposit amounts for large loads are not settled in what we reviewed. Check the current tariff text.
Sources
PJM Inside Lines: PJM Plan Would Cut Interconnection Process Time in Half, 16 November 2026
PJM filing, FERC docket ER27-531, 16 November 2026
BTW Media: PJM's $15 million fast lane for 500 MW, 26 October 2026