Short answer: On 19 November the International Energy Agency (IEA) warned that data center electricity use could roughly double to about 1,000 TWh a year by 2030, and that tight supply chains, local opposition and limited grid capacity could slow new projects (CNBC). It named Texas and Virginia among the places where the capacity of data centers waiting to connect already exceeds current peak demand. For developers, the message is that a site is only as good as its validated path to power. That is the Build approach to data center site selection: source sites, validate power and permits against primary sources, then bundle the services that carry a site into design and construction.
What did the IEA say?
According to CNBC's report on the IEA outlook:
Data center electricity use could reach around 1,000 TWh a year by 2030 under the IEA's Stated Policies Scenario.
Tight supply chains, local opposition and limited grid capacity could slow construction.
The IEA cited large data center pipelines in Texas, Virginia, Finland and the U.K. In several regions, the combined capacity of data centers waiting to connect exceeds current peak demand.
Without grid upgrades, new projects could face longer waits to connect, and networks could become more congested.
Peak electricity demand is projected to rise 40% to 50% by 2035, and supplies of copper, cables and transformers are already tight.
S&P Global reported that the figures come from the IEA's World Energy Outlook 2026 and that grid connection queues are measured in years in several markets (S&P Global).
Why does a queue bigger than peak demand matter?
It means most of the queue will not connect on the schedule its sponsors expect. The IEA's earlier analysis notes that connection queues contain duplicative or speculative projects, and that many jurisdictions are reforming queues with stronger entry requirements, maturity assessments, financial commitments and milestone-based release of capacity (IEA, Powering Artificial Intelligence).
For a developer, two things follow:
A queue position is not a power date. If the queue is larger than the grid, the useful question is where your project sits among credible projects, and what upgrades stand between it and energization.
Rules are moving toward proof. Queue reforms reward projects that can show site control, studies and commitments. Evidence gathered early becomes an advantage, not paperwork.
What does this change for site selection?
| Before | Now |
|---|---|
| Screen for proximity to substations and lines | Confirm deliverable capacity and its date, not only proximity |
| Treat a queue position as progress | Test the position against queue size, upgrades and reform rules |
| Assume equipment arrives on time | Plan for long-lead transformers, switchgear and cables |
| Expect approval to follow power | Treat local opposition and water as schedule risks from day one |
This table is Build's framing of the IEA findings, not an IEA table. The gap between nameplate and real capacity is covered in available vs deliverable capacity, and the evidence that proves it in data center power analysis.
What about Texas and Virginia specifically?
Both are named in the IEA's examples of large pipelines. In Texas, state agencies have also been reviewing how data centers affect communities; see Texas resumes data center permits. In PJM, which covers Northern Virginia, new rules for large loads are arriving; see PJM fast energization and PJM ride-through rules. In both markets, a site with a validated power path is scarcer than a site with land.
What should developers do now?
Validate power before land spend. Get the utility's view of capacity, the upgrade path and the date in writing where possible. Our explainer on will-serve letters covers what they do and do not prove.
Price in equipment lead times. Long-lead items belong in preconstruction, not construction. See data center construction.
Plan for the community. Water use, noise and visual impact decide approvals as often as power does.
Keep the shortlist live. When one site stalls in a queue, the next validated site should already be ready.
What does Build do?
Build is the development execution engine for infrastructure and data centers, built for quality and speed. We work the way the IEA's warning suggests the market now has to: sites first, then validation of power, zoning, water and fiber against primary sources, then the bundled services that move a passing site into design, engineering and construction. That is what we mean by AI native development.
Key takeaways
The IEA says data center electricity use could roughly double to about 1,000 TWh a year by 2030.
In Texas, Virginia and other markets, the capacity waiting to connect already exceeds current peak demand, so most queued projects will wait.
Validated deliverable power, not land, is the scarce input. Validate it before committing to a site.