Short answer: In its earnings disclosures on 18 November 2026, Nvidia reported up to $118 billion in maximum gross guarantee exposure. Of that, $3.5 billion is land, power and shell guarantees for neocloud providers. Each guarantee takes effect only once its building is complete and ready for service, according to TechTarget and Quartz. So the guarantee rewards sites that can be delivered on time, not sites that merely have a reservation. If you build for neoclouds, the question is no longer only "is there power," it is "can this shell be ready on schedule." Build's AI data center development approach starts there: source the site, validate power and delivery risk, then bundle the services that get the building done.
What did Nvidia actually disclose?
Per The Company Chronicle's reading of Nvidia's CFO commentary, maximum gross exposure as of 25 October 2026 breaks down like this:
| Guarantee | Maximum exposure |
|---|---|
| SB Energy credit support (PORTS-Pike campus, Ohio) | $105.0 billion |
| Power and systems credit support | $9.5 billion |
| Land, power and shell guarantees for neoclouds | $3.5 billion |
| Total | $118.0 billion |
Build arithmetic: the neocloud line is about 3% of the total ($3.5 billion divided by $118.0 billion). Nvidia said it had made no payments under its guarantees as of 25 October.
Is this mostly about neoclouds?
No. HyperFrame Research analyst Stephen Sopko told TechTarget that $105 billion of the $118 billion backs land, power and shell for one campus leased to OpenAI for 20 years, and cautioned against reading the total as exposure to neocloud financing. Separately, Nvidia disclosed $32 billion of commitments under neocloud agreements. Those apply only once the operator secures its own financing and the capacity is deployed and accepted, according to Quartz and TechTarget.
When does a guarantee start?
Not at signing. Quartz reports Nvidia said its guarantees take effect phase by phase, once each related building is completed and ready for service, with the first expected in fiscal 2029. On the earnings call, interim CEO and CFO Colette Kress said that if a customer is delayed or runs into trouble building, "our guarantee doesn't exist anymore," as Quartz relayed it. Nvidia also said it will be selective about backing more as other capital sources mature.
What does a site now need?
Build's view, drawing on these disclosures: a guarantee that only starts when a building is ready for service makes delivery readiness the underwriting question. A site that wants this kind of support should be able to show:
A power path with an energization date. See GPU delivery versus energization date.
Site control and entitlements that will not slip. Zoning, permits and local moratorium risk all move the ready-for-service date.
A shell scope tied to the tenant's requirements. See what a neocloud site needs.
Supporting infrastructure on the same clock. Water, fiber and backup power cannot trail the shell.
Evidence checked against primary sources, not broker claims.
Build is the development execution engine for infrastructure, built for quality and speed. We source sites, validate them, and bundle the services that follow. See AI site selection and Build's site selection services. For the broader choice, read neocloud versus hyperscale site selection.
Key takeaways
Nvidia disclosed up to $118 billion in maximum guarantee exposure, including $3.5 billion for neocloud land, power and shell.
Most of the total, $105 billion, backs one Ohio campus leased to OpenAI.
Guarantees start only when each building is ready for service, so on-time delivery is what lenders and sponsors will test.