Data Center Grid Contracts: What 10 to 20 Years Means

Utilities and grid operators have asked FERC to approve 10 to 20 year contracts that make data centers pay for the transmission upgrades they trigger. Here is what each filing proposes and how to underwrite it while nothing is final.

by Build Team • November 19, 2026 • 6 min read

Short answer: Utilities and grid operators have asked FERC to approve long-term contracts that lock data centers into paying for the transmission upgrades they trigger. According to Latitude Media (18 November 2026), a PJM data center would commit to pay for at least 80% of the transmission service it requests for a minimum of 10 years, backed by collateral. California and New York utilities propose 15 years. MISO proposes a three-way agreement that runs up to 20 years. None of it is final: FERC has accepted none of these proposals, and comments on several are due 7 December. For developers, the contract term is now a site-selection input. This is how Build approaches data center site selection: source the site, validate the power path including who pays for upgrades, then bundle the services that follow.

What did utilities ask FERC to approve?

The filings answer a FERC show-cause order on large loads. Latitude Media reports that together they ask FERC to endorse a model where a data center signs a long-term contract with the utility that owns the relevant lines before the upgrades it needs get built. Terms differ by region:

Region Proposed term Key feature, as reported
PJM (transmission owners) At least 10 years Pay for at least 80% of requested service; collateral starts at 25% of what is owed and rises to the full amount by the time service begins
California 15 years Utilities propose it; state tariffs set no minimum term today, per Latitude Media
New York 15 years Same proposed term; reported not to take effect until May 2028
MISO Up to 20 years Three-way agreement among MISO, the transmission owner and the data center

Source: Latitude Media, 18 November 2026, and Volt Grid News summarizing it. Trade press reports the filings; we have not reproduced them from the dockets.

How does the MISO version work?

According to Load Factor News, MISO's cost recovery agreements in docket ER27-526 pair a revenue commitment over 20 years with security equal to the upgrade capital cost. Each year MISO compares the customer's commitment with the transmission revenue the load actually produced, and the customer pays any shortfall. Load Factor News works one example: a 500 MW request with $100 million of upgrades produces a $274,048,000 total required revenue commitment. That is the publication's illustration, not a Build estimate.

Why does the term matter for site selection?

A contract term is a fixed cost that starts before the load does. Build arithmetic, for illustration only: if a developer requests 100 MW of transmission service in PJM, the proposed 80% floor means paying for at least 80 MW worth of service for at least 10 years, whether or not the full 100 MW is ever used. A site that looks cheap on land can look different once that commitment and collateral schedule are in the model.

Latitude Intelligence, cited by Latitude Media, also notes the federal proposals are not the same as what states already require. PJM utilities with state tariffs hold data centers to an average minimum of 12 years, so a 10-year federal floor would be shorter. In MISO, utility terms average 15 years, so 20 would be longer. In retail-choice states such as New Jersey and Pennsylvania, the federal agreement could be a data center's only long-term transmission commitment.

What should developers check now?

  1. Do not underwrite either outcome yet. FERC rejected most of PJM's previous large-load plan in October, per Latitude Media, and could narrow these proposals too.

  2. Ask who signs. In PJM the data center signs with the transmission owner. In MISO the agreement is three-way, and only the transmission customer, usually the load-serving utility, applies for service, per Load Factor News.

  3. Model collateral timing. A guarantee that starts at 25% and rises to 100% changes cash needs before the first rack is energized.

  4. Validate the power path first. Term length matters less on a site with no deliverable capacity. See power availability and site selection and FERC's large load interconnection rulemaking.

  5. Track the dates. Comments on several filings are due 7 December, and the Southwest Power Pool was due to file by 20 November, per Volt Grid News.

Build is the development execution engine for infrastructure: it sources sites, validates power, zoning, fiber, water and land against primary sources, and bundles the services that take passing sites toward construction. See AI site selection and Build's site selection services. For related policy context, read PJM Fast Energization: what changes for data centers.

Key takeaways

  • Utilities in PJM, MISO, California and New York have asked FERC for 10 to 20 year large-load transmission contracts. None is approved.

  • PJM: at least 80% of requested service for at least 10 years, with collateral. California and New York: 15 years. MISO: up to 20 years.

  • Treat contract term and collateral as site-selection inputs, and keep the base case on current rules until FERC acts.

Sources

Frequently Asked Questions:

What did utilities ask FERC to approve for data center grid costs?

Long-term contracts that make data centers pay for the transmission upgrades they trigger. Latitude Media reports 10 years minimum in PJM, 15 years in California and New York, and up to 20 years in MISO.

What does the PJM proposal require?

According to Latitude Media, a data center would pay for at least 80% of the transmission service it requests for at least 10 years. Collateral would start at 25% of what it owes and rise to the full amount by the time service begins.

Are these contracts approved?

No. FERC has accepted none of the proposals, and comments on several are due 7 December.

How is the MISO proposal different?

MISO proposed a three-way agreement among itself, the transmission owner and the data center, running up to 20 years, according to Latitude Media.

Does this change how I should pick a data center site?

Yes. Contract term and collateral are costs that start before load does, so they belong in site validation alongside power availability, zoning, fiber and water.

Should I underwrite these terms today?

Keep your base case on current rules until FERC acts, and run the proposed terms as a sensitivity.