Short answer: On 17 November Giga Energy said an undisclosed U.S. AI cloud provider signed a 10-year lease, which Giga valued at about $1 billion, for Project Clay, a 60 MW AI data center in Hunt County, Texas (Giga Energy). Giga says the build will finish in under eight months, using factory-built construction, closed-loop cooling and new electrical infrastructure on dedicated power capacity. Whatever the final schedule, the lesson is that fast builds are decided before construction starts: power that already exists near the site, a design fixed early and permits that face fewer objections. That is the work of data center preconstruction, and it is where Build focuses: sites, then validation, then the bundled services that follow.
What did Giga announce?
From Giga's release and Reuters coverage:
| Item | Detail |
|---|---|
| Project | Project Clay, a 60 MW GigaBase AI data center |
| Location | Hunt County, Texas, on a campus of about 30 acres |
| Tenant | An undisclosed U.S.-based AI cloud provider |
| Lease | 10 years, valued by Giga at about $1 billion |
| Schedule | Ground broken in July; build in under eight months; ready for service in spring 2027 |
| Power | New electrical infrastructure that taps underutilized capacity on dedicated power infrastructure, designed not to draw on distribution capacity serving existing homes and businesses |
| Cooling | Fully closed-loop system that does not use municipal water or groundwater to cool IT equipment |
| Construction | Factory-first model: much of the facility is built off-site and assembled locally |
Giga describes the schedule as less than half the time of traditional builds. That is the company's claim, not an independent benchmark.
What actually makes a data center build fast?
Construction speed is mostly set in preconstruction. In Build's view, four conditions make a short build possible:
Power that does not wait on a long upgrade. Project Clay uses existing capacity on dedicated infrastructure. A site that needs a new transmission line cannot build in eight months, however fast the building goes up. The IEA notes new transmission lines can take four to eight years in advanced economies (IEA, Energy and AI).
A design fixed early. Factory-built modules only save time when the design basis, density and cooling are decided before fabrication. Late changes erase the gain. See data center design.
Long-lead equipment ordered on time. The IEA says wait times for transformers and cables have doubled in the past three years. Procurement has to start in preconstruction.
Fewer approval objections. Closed-loop cooling with no draw on local water answers one of the most common community concerns. Texas has been reviewing data center community impacts; see Texas resumes data center permits.
Is a 60 MW block a model for larger campuses?
It is a model for phasing. Smaller blocks can energize sooner and earn revenue while later phases wait for power. Larger campuses usually depend on bigger utility upgrades, so they often deliver capacity in stages; see power ramp schedules. The fast part of a large campus is often its first block, sized to the power available now.
What should developers copy?
Size the first phase to deliverable power, not to the land. Validate what the utility can serve and when. See available vs deliverable capacity.
Lock the design basis before ordering. Density, cooling method and redundancy level decide what can be prefabricated.
Treat water as a permit strategy. Closed-loop or low-water cooling can reduce friction with communities and regulators.
Start procurement in preconstruction. Generators, switchgear and transformers set the schedule as often as the building does. Our preconstruction explainer covers the phase.
What does Build do?
Build is the development execution engine for infrastructure and data centers, built for quality and speed. We source sites with a credible power path, validate them against primary sources, then bundle the preconstruction services, including design basis, permitting inputs and long-lead planning, that let construction start on a site that holds up. We do development work only and hand the contractor a validated site and design basis. That is AI native development applied to speed.
Key takeaways
Giga Energy says its 60 MW Project Clay in Hunt County, Texas, leased for 10 years, will be built in under eight months and enter service in spring 2027.
Speed came from decisions made before construction: existing power capacity, factory-built design and water-free cooling.
Developers who want fast builds should validate power and fix the design basis in preconstruction.