Short answer: On 16 November 2026, PJM filed tariff revisions at FERC (docket ER27-522) that would require data centers and other Large Computational Loads to meet minimum voltage and frequency ride-through requirements, meaning they must stay connected through defined grid disturbances. A Large Computational Load is a Large Load, which is 50 MW or more at a single site, with at least 25 MW of maximum load served through power electronic conversion equipment. PJM asked for a 16 January 2027 effective date. The rules are a proposal until FERC acts. They matter for site selection and engineering because compliance becomes a condition of connecting. See data center power analysis.
What is ride-through?
Ride-through is the ability of a load to stay connected, without involuntary block loss of load, when the grid has a voltage or frequency disturbance. PJM's concern, stated in its filing, is that Large Computational Loads may pose heightened operational risks to the bulk electric system during grid disturbances.
Who counts as a Large Computational Load?
Two tests apply, both from PJM's filing and reporting on it:
It must be a Large Load. FERC accepted PJM's Large Load definition effective 12 October 2026: a cumulative peak load of 50 MW or more at a single electrical site. Affiliated facilities within a one-mile radius count as one site.
At least 25 MW must be served through power electronic conversion equipment. This is the feature of data center loads that distinguishes them from, say, a steel mill.
Illustrative examples applying those two tests (Build's reading, not PJM guidance):
| Scenario | Large Load? | Large Computational Load? |
|---|---|---|
| 60 MW campus, 30 MW through power electronic conversion | Yes | Yes |
| 60 MW campus, 20 MW through power electronic conversion | Yes | No, under the 25 MW test |
| 40 MW single site | No | No |
| Two affiliated 30 MW buildings within one mile | Yes, counted as one 60 MW site | Depends on how much is served through power electronic conversion |
PJM also left room to define details in its manuals, so confirm how it will measure conversion equipment load for your project.
What would the rules require?
PJM's filing does two things:
It sets the framework for minimum voltage ride-through and frequency ride-through requirements, with detailed standards promulgated through PJM manuals.
It sets a framework for other operational requirements to be established in the manuals: ramp rates, electromagnetic transient performance, auxiliary equipment and protection systems, maintenance outage protocols, remote disconnection capability, and telemetry and data exchange.
PJM's September 2026 draft manual language, which is a draft and not final, shows the shape of a voltage ride-through curve: continuous operation between 0.90 and 1.10 per unit voltage, at least 2 seconds between 0.80 and 0.90, at least 0.5 seconds between 0.50 and 0.80, and at least 0.25 seconds below 0.50. The draft also bars load-shedding or transfer-to-backup schemes that disconnect the load solely because of a count of voltage sags or swells where the load is required to ride through. Final values will come through the manuals.
When would it apply?
| Item | Detail |
|---|---|
| Filing | 16 November 2026, FERC docket ER27-522 |
| Requested effective date | 16 January 2027 |
| New facilities | Must demonstrate compliance to connect and operate |
| Existing facilities | One year from the effective date, or one year from the start of commercial operation, whichever is later |
Trade press reports that PJM asked FERC to rule by 15 January 2027, and that the rule would reach roughly 10 GW of computational load already in PJM's footprint.
What does this mean for data center developers?
Treat ride-through as an engineering and procurement requirement. Power conversion equipment, controls and protection settings need to be specified for it. Confirm with vendors and your engineer of record.
Check backup transfer logic. Schemes that move load to generators on every sag may conflict with the draft language.
Add it to site and utility diligence. Compliance is a condition of service in PJM, so it belongs with power validation. See power availability and site selection and PJM load growth and underwriting.
Watch the final manuals. Numeric limits are not final.
Read it with the study-process filing. PJM filed Fast Energization the same day. See PJM Fast Energization: what changes for data centers.
Build validates power deliverability and the operating requirements attached to it, with every finding traced to a source, before a site is committed. It then bundles the engineering and delivery services that follow. See AI native development.
Key takeaways
PJM filed ride-through requirements at FERC on 16 November 2026 in docket ER27-522, with a requested effective date of 16 January 2027.
A Large Computational Load is a Large Load of 50 MW or more at one site with at least 25 MW served through power electronic conversion equipment.
New facilities must show compliance to connect. Existing facilities get one year from the effective date or from commercial operation, whichever is later.
Numeric voltage and frequency limits will be set in PJM manuals. The September curve is a draft.