What Does BAAJA Permitting Reform Mean for Data Center and Energy Developers?

The Senate passed the BAAJA permitting bill 62-33 and the House has not voted. What it would change for data center and energy developers, and what it would not.

by James SE • November 28, 2026 • 6 min read

Short answer: If it becomes law, the Bipartisan American Affordability and Jobs Act (BAAJA) would make federal permitting more predictable and give developers a clearer route to transmission. It would not change state and local zoning, switch off the interconnection queue overnight or weaken the substantive environmental laws. As of November 28, 2026 the Senate has passed it and the House has not voted, so the sensible move is to plan for both outcomes and price the delay you cannot control.

What is BAAJA and where does it stand?

BAAJA is a near 500 page federal permitting package, carried on H.R. 2347. The Senate passed it 62-33 on November 19, 2026 and sent it back to the House on November 24. The House Rules Committee is scheduled to meet on November 30 and floor votes are reported for the week that follows, but the outcome is not settled. Both chambers must agree on the same text before it goes to the President, who has said he will sign it.

Support and opposition both cross party lines. Supporters point to faster approvals, a stronger grid and lower power costs. Critics raise concerns about tribal consultation, public lands and limits on public challenges. Both views are worth reading before you plan around the bill. Sources: Congress.gov, House Rules Committee and NPR.

Why does litigation risk matter more than the review itself?

A project can pass its review and still lose years in court. A Stanford study of 355 major energy and transport projects that completed a federal environmental impact statement between 2010 and 2018 found that 64% of solar projects faced litigation and 32% were ultimately canceled. For transmission lines, 31% were litigated. Source: Bennon and Wilson, Environmental Law Reporter, 2023. Those are not data centers, but data centers depend on the same power projects.

For an investor or lender the problem is not only the delay. It is that nobody can say how long the delay will be. In the Senate-passed text, claims over covered federal environmental reviews must be filed within 150 days, generally by parties that commented during the process and can show direct harm. The text also bars federal agencies from revoking or materially altering permits for projects that already hold them, with listed exceptions. Source: Senate-passed text of H.R. 2347.

Does it fix the power problem for data centers?

Only partly, and not quickly. Power decides most data center sites, and the power analysis is usually the first gate a site must pass. The Senate-passed text addresses the grid in several ways:

  • It expands FERC's authority to permit certain interstate transmission lines, as summarized by the Congressional Research Service.

  • It adds provisions on transmission planning and a consolidated planning process.

  • It directs FERC to expedite generator interconnection queues.

The Institute for Progress explainer puts the median wait for new generation in the interconnection queue at roughly five years today. The bill directs FERC to write rules aimed at that wait. Rules take time to write, test and put into practice, so plan on years, not months. Sources: IFP explainer and Congress.gov summary.

How would it change the cost of connecting a data center?

This part may matter more than the litigation changes. For data centers that interconnect on or after enactment, the Senate-passed text says no part of the incremental cost of serving them may be pushed onto other customers. Utilities must design rates to recover that cost even if the data center later exits its contract, and must require reasonable financial assurances before building the upgrades that serve it.

States get room to go further. They may hold open seasons or competitive solicitations for connection, require a data center to procure new generation or make service conditional on limited transmission service that caps when and how much power it can draw. For anyone underwriting a project, that moves cost and risk onto the developer earlier and rewards sites where power is already planned and paid for. Source: Senate-passed text of H.R. 2347.

What changes and what does not?

Would change if enacted Would not change
Litigation 150-day filing window and comment and harm requirements for covered federal environmental reviews Exposure on projects with no federal permit
Permits Limits on agencies revoking or materially altering permits already in effect The substantive environmental laws
Transmission Wider FERC permitting authority for certain interstate lines and new planning requirements State and local zoning and land use approvals
Interconnection FERC directed to expedite generator queues The queue itself, until those rules exist and take effect
Data center costs Cost recovery and financial assurance rules, plus state options on top Data centers that interconnected before enactment

How should developers plan while the vote is pending?

Plan for two regimes and keep both live in the model. Four steps help:

  1. Screen every site for a federal nexus. Does any part of the project need a federal permit, federal land or a federal crossing? If not, the review changes matter less to you than the power that serves the site. A zoning and permitting review shows which approvals sit with the state or county.

  2. Map the transmission path, not just the substation. Ask which lines serving the site could be affected by the new FERC authority and which still depend on a state.

  3. Log every dependency on a rule that does not exist yet. FERC rulemaking is a timeline risk. Write down each assumption that relies on it and carry it through due diligence.

  4. Test the cost rules. Model the incremental cost and financial assurance requirements before you commit to a site, and treat a fatal flaw analysis as the place to catch a power path that no longer pencils.

This is the kind of work we do as a vertically integrated development firm. We run accelerated infrastructure development with our own technology stack, so a regulatory change becomes a question about specific sites with a specific answer in days, not a memo. See how we approach data center site selection.

Related reading

This article explains a bill for developers and is not legal advice or a position on pending legislation. Talk to counsel on specific projects.

Frequently Asked Questions:

Is BAAJA law?

No. As of November 28, 2026 the Senate has passed it 62-33 and the House has not voted. Both chambers must agree on the same text before it goes to the President.

Does BAAJA apply to my data center?

Partly. The permitting and litigation provisions matter for projects that need federal approvals. The cost recovery rules in the Senate-passed text apply to data centers that interconnect on or after enactment. State and local approvals are separate.

Will BAAJA shorten interconnection queues?

It directs FERC to expedite generator interconnection queues, but it does not shorten the queue on the day it is signed. Expect the effect to show up over years as rules are written and put into practice.

Does BAAJA weaken environmental protection?

Supporters say it keeps the substantive protections and changes procedure and litigation. Critics say it limits public and tribal input and makes permits harder to challenge or change. Read the final text and the arguments on both sides.

What should developers do while the House vote is pending?

Screen sites for a federal nexus, map transmission paths, log dependencies on future FERC rules and test the data center cost rules. Keep both outcomes in the timeline.