Short answer: TVA now charges new and expanding data center loads above 5 MW a Capacity Commitment Charge. In its fiscal 2026 annual report, TVA says the rate is approximately $1.5 million per MW of requested capacity above 5 MW. TVA signed its first agreement under the charge on 10 November 2026: $1.7 billion in aggregate payments, with $31 million due at signing and the rest paid over 59 further installments. For developers in the Tennessee Valley, capacity is no longer only a queue position. It carries a price that is paid up front and over time.
What is TVA's Capacity Commitment Charge?
According to a TVA subsequent-event note filed with the SEC, TVA established a Capacity Commitment Charge (CCC) effective 1 October 2026 for new and expanding data center loads above 5 MW. The charge is based on requested capacity above that 5 MW line. TVA says the rate "reflects TVA's current cohort-based pricing methodology, which may be revised for future customer cohorts."
| Term | What TVA's filing says |
|---|---|
| Who pays | New and expanding data center loads above 5 MW |
| Effective date | 1 October 2026 |
| Rate in the first agreement | Approximately $1.5 million per MW of requested capacity above 5 MW |
| Future rates | May be revised for future customer cohorts |
What did TVA's first deal look like?
TVA entered into its first CCC agreement on 10 November 2026. The same filing says TVA is entitled to aggregate payments of $1.7 billion. An initial payment of $31 million is due on execution, and the remaining balance is paid over 59 subsequent installments, so 60 payments in total. TVA did not name the customer in the filing.
RTO Insider reported on 19 November 2026 that TVA had signed its first data center agreement under a recently approved large load tariff. Energy Central summarized the structure as roughly $1.5M per MW of requested capacity over three to five years, then $1.7B over 60 installments for the first deal. We rely on the SEC filing for the numbers above because it is TVA's own disclosure.
Is $1.5M per MW a fixed price?
No. Two words in TVA's filing matter. First, the rate is "approximately" $1.5 million per MW. Second, it is tied to a cohort-based method that TVA says may be revised for future cohorts. A developer who signs later should not assume the same number.
The filing also describes how TVA will book the money. It expects to record the initial payment as a receivable and a matching regulatory liability in November 2026, and it is still evaluating the amortization period.
What does the charge mean for underwriting?
The CCC turns a soft question, "can the grid serve this load," into a hard one: "what do we pay to hold the capacity, and when." That changes three parts of a development budget.
Cash at signing. TVA's first deal had an initial payment of $31 million at execution. A developer needs that cash before energization, not at it.
A long payment stream. With 59 later installments, the charge behaves like a financing obligation. It belongs in the pro forma next to debt service.
Capacity you request is capacity you pay for. Because the charge applies to requested capacity above 5 MW, an inflated request costs real money. A developer who asks for 400 MW to hold options pays for 400 MW less the first 5.
A simple way to sanity check a quote: take requested MW, subtract 5, multiply by the rate. That is arithmetic on the disclosed rate, not a TVA quote for any specific project.
How does this compare with other large-load tariffs?
TVA's charge sits in a wider trend: utilities and grid operators are asking large loads to commit money and capacity earlier. Our guide to large load tariffs as an underwriting variable covers the common features of these tariffs, such as minimum bills, long terms and exit fees. TVA's approach is notable because the capacity price is stated per MW and paid in installments over a long schedule.
Other examples of the same direction:
Georgia's PSC allows 5 to 15 year contracts and minimum billing for new customers above 100 MW, according to the PSC's January 2025 release.
PJM's Fast Energization proposal moves readiness deposits earlier, according to PJM.
What should a developer ask TVA or the local power company?
Which cohort will my request fall into, and what rate applies to that cohort?
What counts as requested capacity, and can it be staged?
What happens to payments if the project is delayed, resized or cancelled?
How do the installment dates line up with my energization date?
TVA's public filing does not answer all of these, so get the answers in writing before committing land or equipment orders.
What Build does here
Build is a vertically integrated development firm. Using our own technology stack, we take data center projects from site to shovel-ready, including the power path and the cost of securing it. For a Tennessee Valley project, the client gets a capacity request sized to the real load, with its payment schedule laid out against the build timeline. Related technical background lives in our data center engineering guide.
Key takeaways
TVA's Capacity Commitment Charge applies to new and expanding data center loads above 5 MW, effective 1 October 2026.
The first agreement, signed 10 November 2026, totals $1.7 billion: $31 million at signing plus 59 installments.
The rate is approximately $1.5 million per MW of requested capacity above 5 MW and may change for future cohorts.
Treat the charge as a financing item in underwriting, not a footnote.
Sources
TVA subsequent events note (SEC filing), fiscal year ended 30 September 2026
RTO Insider, "TVA Reports Major Data Center Deal", 19 November 2026
Energy Central, TVA data center deal summary, 22 November 2026
Georgia PSC news release, 23 January 2025
PJM Inside Lines on Fast Energization, 16 November 2026