---
title: "What Is ERCOT Batch Zero? The Dec 10 Audit Explained | Insights | Build"
description: "Batch Zero is ERCOT's one-time study of large loads of 75 MW or more under PGRR 145. ERCOT has paused energization of new data centers and crypto facilities at that size until it files eligibility and community-impact reports with the PUCT on 10 December 2026. This explainer covers what Batch Zero is, what ERCOT is checking and what developers should do before those reports land."
url: https://build.inc/insights/what-is-ercot-batch-zero-dec-10-audit
---

[Industry](https://build.inc/insights?category=industry)

# What Is ERCOT Batch Zero? The Dec 10 Audit Explained

Batch Zero is ERCOT's one-time study of large loads of 75 MW or more under PGRR 145. ERCOT has paused energization of new data centers and crypto facilities at that size until it files eligibility and community-impact reports with the PUCT on 10 December 2026. This explainer covers what Batch Zero is, what ERCOT is checking and what developers should do before those reports land.

by Build Team • November 25, 2026 • Updated () => { const published = new Date(data.article.publishedAt); const modifiedRaw = data.article.lastModified ? new Date(data.article.lastModified) : null; if (!modifiedRaw || Number.isNaN(modifiedRaw.getTime())) return void 0; if (modifiedRaw.getTime() <= published.getTime()) return void 0; return modifiedRaw.toLocaleDateString("en-US", { year: "numeric", month: "long", day: "numeric" }); } • 6 min read

**Short answer:** Batch Zero is ERCOT's one-time transitional study of large loads of 75 MW or more, created under Planning Guide Revision Request (PGRR) 145. After a 3 August 2026 directive from Gov. Greg Abbott, ERCOT paused the study, delayed final classification of those loads, and paused approvals to energize new data centers and crypto facilities of 75 MW or more. ERCOT will file two reports with the Public Utility Commission of Texas (PUCT) by 10 December 2026: a Batch Zero Eligibility Verification Report and a Community Impact Review Report. Those filings decide which projects stay in Batch Zero. They are not a new interconnection product, and they do not, by themselves, restart energization.

## What is Batch Zero?

Batch Zero is the first, one-time grouping of large loads that ERCOT is studying under PGRR 145. In ERCOT, a large load is 75 MW or more. The revision set a process for classifying those projects, studying their impact on the grid, and offering capacity. As originally adopted, PGRR 145 required ERCOT to issue final classifications by 7 August 2026 and to deliver study results and offer capacity no later than 9 April 2027.

That sequence was interrupted. On 3 August 2026, Governor Abbott directed the PUCT and ERCOT to complete a comprehensive verification and audit of data centers advancing through the interconnection process before allowing those loads to proceed. ERCOT issued a market notice the same day pausing the Batch Zero study process and delaying final classification of all large loads. It also paused approvals to energize new data centers and virtual currency mining facilities of 75 MW or more.

ERCOT later gave interconnecting transmission service providers a provisional Batch Zero classification (base, studied or excluded) on 3 September 2026. Final inclusion or exclusion, ERCOT said, would wait for the eligibility verification and would be provided in December. ERCOT also said it was still determining the impact on the original 9 April 2027 study deadline.

## What are the 10 December reports?

ERCOT has told the PUCT it will file two reports by 10 December 2026:

| Report | What it covers |
| --- | --- |
| Batch Zero Eligibility Verification Report | Which large loads of 75 MW or more remain eligible for Batch Zero |
| Community Impact Review Report | Information collected on the community impact of data center and crypto loads, including medium loads (25 MW to under 75 MW) as well as large loads |

The findings are expected to be discussed at the PUCT's 17 December 2026 open meeting. See [Texas resumes data center permits](https://build.inc/insights/texas-resumes-data-center-permits) for how this relates to the TCEQ environmental-permit pause, which the agency resumed in mid-November, and why a restarted air or stormwater review is not the same as an approval to energize.

## What is ERCOT checking in the eligibility audit?

The eligibility review is a documentation test against Planning Guide Section 9, not a new power-flow study. In a 5 November 2026 update to the PUCT, ERCOT said transmission service providers had timely submitted all first-round requests for information, and that ERCOT teams and outside counsel had reviewed responses from 257 developers, covering about 5,140 questions. It was issuing a second, shorter round of developer-specific questions, expected to go to 80% of the developers, with a five business day deadline so they could explain deficiencies.

ERCOT said the review looks at site control evidence, agreements, financial security (including letters of credit, bank ratings and parental or corporate guaranties), and long-lead-time equipment and studies for system upgrades. Although the review was not finished, ERCOT told the PUCT that common issues were already emerging: lack of documentation to establish affiliate relationships, inability to demonstrate site control, inability to show that long-lead-time equipment had been ordered and would be delivered before energization, and difficulty confirming the amount of financial security posted.

Projects that fail verification, or that do not respond in time, can be left out of Batch Zero. Inclusion is not automatic.

## What is still paused?

Two tracks are easy to confuse:

1.  **Energization of new large-load data centers and crypto facilities.** ERCOT has paused approvals to energize new data centers and crypto facilities of 75 MW or more until the eligibility verification and the community-impact review are complete. The pause, as ERCOT described it, does not apply to medium loads (25 MW to under 75 MW) or to large loads that are not data centers or crypto facilities. Confirm the status of any specific project with ERCOT and the interconnecting utility.

2.  **TCEQ environmental permits.** Those are a separate state process. TCEQ resumed its normal data center permit review in mid-November 2026 after a pause ordered on 21 September. A resumed permit review does not, on its own, lift ERCOT's energization pause.

For how Texas grid access works more broadly, see [Texas data centers and the ERCOT grid](https://build.inc/insights/texas-data-centers-ercot-grid) and [what a large load is](https://build.inc/insights/what-is-a-large-load).

## What should developers do before 10 December?

1.  **Confirm whether the project is in Batch Zero, and at what provisional classification.** The 3 September provisional list is not the final word.

2.  **Close documentation gaps now.** Site control, affiliate relationships, financial security and evidence that long-lead equipment will arrive before energization are the items ERCOT has already flagged.

3.  **Do not treat a TCEQ permit as an energization date.** Keep the power path current with the utility and ERCOT. See the [interconnection queue guide](https://build.inc/insights/interconnection-queue-data-center-developer-guide).

4.  **Hold schedule contingency through mid-December.** The 10 December filings and the 17 December PUCT meeting are the next decision points for eligibility and for any change to the energization pause.

5.  **Prepare the community-impact file.** Water, cost sharing, on-site power, neighbor impacts and ownership were part of the information ERCOT collected. Having those answers ready is useful even after the report is filed.

## How Build helps

Build is a vertically integrated development firm. We use our own technology stack and proprietary data to take data center projects from site to shovel-ready, with one accountable team owning the outcome. In Texas, that includes checking a site's ERCOT path, large-load status and permit dependencies before the site is committed, then carrying the projects that pass through diligence, [engineering](https://build.inc/learn/ai-engineering/data-centers) and preconstruction. See [data center development](https://build.inc/markets/data-center) and [Build's services](https://build.inc/services).

## Key takeaways

-   Batch Zero is ERCOT's one-time PGRR 145 study of loads of 75 MW or more, not a standing interconnection product.

-   ERCOT has paused energization of new data center and crypto facilities of 75 MW or more until it finishes the eligibility verification and community-impact review.

-   Two reports are due to the PUCT by 10 December 2026, with discussion expected at the 17 December open meeting.

-   Final Batch Zero inclusion depends on passing the documentation audit, including site control, financial security and long-lead equipment evidence.

-   A restarted TCEQ permit review is not the same as an approval to energize.

## Sources

-   [ERCOT, Batch Zero Update, 14-15 September 2026 Board of Directors meeting](https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf)

-   [ERCOT, Batch Zero Eligibility Verification Process Update, PUCT open meeting, 5 November 2026](https://www.ercot.com/files/docs/2026/11/05/ERCOT-Verification-RFI-Update.pdf)

## Frequently Asked Questions:

What is ERCOT Batch Zero?

It is ERCOT's one-time transitional study of large loads of 75 MW or more under Planning Guide Revision Request 145. It classifies those projects, studies their grid impact and is the path to an offer of capacity.

Why did ERCOT pause Batch Zero?

On 3 August 2026, Gov. Greg Abbott directed ERCOT and the PUCT to verify and audit data centers in the interconnection process before those loads proceed. ERCOT paused the study, delayed final classification, and paused approvals to energize new data centers and crypto facilities of 75 MW or more.

What happens on 10 December 2026?

ERCOT will file a Batch Zero Eligibility Verification Report and a Community Impact Review Report with the PUCT. The findings are expected to be discussed at the PUCT's 17 December open meeting. Final inclusion or exclusion from Batch Zero follows those reports.

Does the pause apply to every Texas data center?

ERCOT described the energization pause as applying to new data centers and crypto facilities of 75 MW or more. Medium loads (25 MW to under 75 MW) and large loads that are not data centers or crypto facilities were not included in that description. Confirm each project's status with ERCOT and the utility.

Is a TCEQ permit enough to turn a project on?

No. TCEQ resumed environmental permit review in mid-November 2026, but ERCOT's energization pause is a separate track and remains in place until the verification and community-impact review are complete.

What is ERCOT looking for in the eligibility audit?

Documentation required by Planning Guide Section 9, including site control, financial security and evidence that long-lead equipment will be delivered before energization. ERCOT has already flagged gaps in those areas, and in affiliate-relationship documentation, as common issues.

[Industry ### What Is Non-Firm Transmission Service for Data Centers? November 25, 2026](https://build.inc/insights/what-is-non-firm-transmission-service-data-centers)[Industry ### Spain's Data Center Decree: What Developers Must Prove November 24, 2026](https://build.inc/insights/spain-data-center-decree-what-developers-must-prove)[Industry ### Six Grid Operators' Large-Load Plans: What Changes November 24, 2026](https://build.inc/insights/six-grid-operators-large-load-plans-ferc)
