---
title: "Six Grid Operators' Large-Load Plans: What Changes | Insights | Build"
description: "Six U.S. grid operators filed large-load reforms at FERC between 13 and 20 November 2026. POWER reports they generally use a 50 MW threshold, but they differ on non-firm service, bring-your-own-capacity rules and upgrade costs. This guide compares the plans, the curtailment prices and the requested effective dates."
url: https://build.inc/insights/six-grid-operators-large-load-plans-ferc
---

[Industry](https://build.inc/insights?category=industry)

# Six Grid Operators' Large-Load Plans: What Changes

Six U.S. grid operators filed large-load reforms at FERC between 13 and 20 November 2026. POWER reports they generally use a 50 MW threshold, but they differ on non-firm service, bring-your-own-capacity rules and upgrade costs. This guide compares the plans, the curtailment prices and the requested effective dates.

by Build Team • November 24, 2026 • 7 min read

**Short answer:** Six U.S. regional grid operators filed large-load tariff reforms with the Federal Energy Regulatory Commission (FERC) between 13 and 20 November 2026: ISO New England (ISO-NE), CAISO, MISO, NYISO, PJM and Southwest Power Pool (SPP). [POWER magazine](https://www.powermag.com/five-grid-operators-respond-to-ferc-with-distinct-plans-for-large-load-integration/) reports that they generally use a 50 MW threshold to identify a large load, but their plans differ sharply on three things a data center developer has to underwrite: whether a project can energize early on non-firm service, whether it must bring its own generating capacity, and who pays for grid upgrades. None of it is final. Every proposal is still subject to FERC review, and most changes would not take effect before 2027.

## Who filed, and when?

The filings answer six show-cause orders FERC issued on 18 June 2026, which found that existing regional tariffs may be unjust and unreasonable in how they treat large loads. FERC set a deadline of 16 November for five operators and 20 November for SPP, according to [POWER](https://www.powermag.com/five-grid-operators-respond-to-ferc-with-distinct-plans-for-large-load-integration/).

| Grid operator | Filed | Headline proposal |
| --- | --- | --- |
| ISO-NE | 13 Nov | Firm, non-firm and interim contract demand service; Bring Your Own New Capacity (BYONC) for firm service |
| CAISO | 16 Nov | Flexible Interim Load Interconnection (FILI) for earlier energization; no customer-specific capacity requirement |
| MISO | 16 Nov | Interim network service plus Grid Responsive Integration Transmission Service (GRITS), a long-term firm and non-firm mix |
| NYISO | 16 Nov | Large Load Integration Procedures (LLIP) with non-firm withdrawal service and a resource adequacy test |
| PJM (and PJM transmission owners) | 16 Nov | A 12-month Fast Energization Process; ride-through rules; a 50 MW cap on behind-the-meter netting; a cost recovery agreement from the transmission owners |
| SPP | 20 Nov | Price Adaptive Load Service (PALS) and a Load Safe Harbor Limit on upgrade funding |

ERCOT is not part of this. Its transmission rates fall outside FERC's jurisdiction, so it did not receive the June orders.

The broader rulemaking also stays open. FERC kept [docket RM26-4](https://www.ferc.gov/rm26-4) open after the June orders. That docket started from an October 2025 Department of Energy proposal in which large loads were generally defined as demand above 20 MW.

## Do all six use a 50 MW threshold?

Mostly, but check the tariff. POWER's summary is that the operators "generally use a 50-MW threshold to identify large loads." The 50 MW figure also shows up in specific rules: ISO-NE would apply its new requirements to existing facilities whose gross peak demand grows by 50 MW or more above their exempt demand, and PJM would cap the daily demand reduction from retail behind-the-meter generation at 50 MW at a single electrical location.

Other numbers matter too. MISO's Large Load Addition Resource Study applies to loads of at least 200 MW that have partnered with a generator for at least 15 years. NYISO's resource adequacy test lets a load that degrades adequacy by 25 MW or less get its full firm request. And outside these filings, other lines are in use, as our explainer on [what counts as a large load](https://build.inc/insights/what-is-a-large-load) sets out.

We could not confirm a 50 MW eligibility threshold in each operator's tariff text from the filings themselves, so treat 50 MW as the common reference point, not a uniform rule.

## What changes for a data center developer?

### 1\. Non-firm service could let projects energize earlier

Four operators propose price-based curtailment of large loads that take non-firm service:

| Operator | Service | When non-firm load is curtailed |
| --- | --- | --- |
| MISO | GRITS | Locational price above $100/MWh, and during capacity advisories |
| ISO-NE | Interim and non-firm contract demand service | Redispatch above $250/MWh |
| NYISO | Non-firm withdrawal service | $200/MWh maximum bid price, plus operator-directed curtailment |
| SPP | PALS | Dispatched to zero above a $25/MWh bid cap |

Source: [POWER](https://www.powermag.com/five-grid-operators-respond-to-ferc-with-distinct-plans-for-large-load-integration/). ISO-NE said its $250/MWh price occurred in about 1% of hours from 2021 to 2025. MISO said historical data suggest its threshold would permit service in more than 95% of hours.

For underwriting, this is the big shift. A site that cannot get firm service for years may be able to energize on non-firm service first, if the tenant can tolerate interruptions or the site has backup generation. See [behind-the-meter power for data centers](https://build.inc/insights/behind-the-meter-data-center-power) and [data center demand response](https://build.inc/insights/data-center-demand-response-2026).

### 2\. Some regions want you to bring capacity

Resource adequacy rules split the operators:

-   **ISO-NE:** firm service would require the customer to designate sufficient new capacity resources, with interim service until they are running.

-   **NYISO:** a load that harms resource adequacy can secure firm rights through long-term arrangements with qualifying resources that need not be co-located.

-   **SPP:** PALS loads would carry no additional resource adequacy obligation.

-   **CAISO:** argues a customer-specific procurement requirement is unnecessary under its existing framework.

-   **MISO:** firm load keeps existing capacity obligations; non-firm GRITS demand may be excluded from them.

### 3\. Upgrade costs and revenue commitments are moving to the customer

-   **SPP** would cap upgrade funding through its transmission rates at the lesser of $500,000 per MW of requested load or $25 million per request. Costs above that would be directly assigned to the customer for up to 40 years, whether or not the load is energized.

-   **PJM's transmission owners** propose a cost recovery agreement with a minimum 10-year term and revenue commitments of 80% to 100% of the firm service benchmark, with credit support based on 100%.

-   **PJM** would run generation and large-load requests through one 12-month study cycle, and adds ride-through requirements for large computational loads.

These terms change what a site's power path is worth. Our posts on [PJM load growth](https://build.inc/insights/pjm-load-growth-data-center-underwriting) and [large-load tariffs in underwriting](https://build.inc/insights/large-load-tariffs-data-center-underwriting) show how to model them.

## When would the changes take effect?

Not soon, and not all at once. Requested dates reported by POWER:

| Operator | Requested timing |
| --- | --- |
| NYISO | LLIP from 1 February 2027; most market changes 1 June 2028 |
| CAISO | Most reforms 16 February 2027; settlement changes 30 April 2028 |
| SPP | Study and funding changes February 2027; PALS targeted for Q2 2028 |
| PJM | Most transmission service changes 16 March 2027; Fast Energization Process after the current cycle's second decision point, expected late November 2027 |
| ISO-NE | New study applications from 1 June 2027; new services from 1 June 2028 |
| MISO | GRITS not before 1 January 2029 |

All dates depend on FERC approval, and several reforms need further tariff filings, stakeholder work or software changes.

## What developers should do now

1.  **Map each target site to its operator and utility.** The service options, deposits and capacity rules now differ by region.

2.  **Decide early if non-firm service is acceptable.** It can pull energization forward but changes tenant terms and backup design.

3.  **Price the upgrade exposure.** Cost caps and revenue commitments can turn a cheap site into an expensive one.

4.  **Check the power date against the requested effective dates.** A plan that relies on a 2028 service is a plan that relies on FERC approving it.

5.  **Keep watching.** POWER notes its analysis is initial and the filings are under review.

Our [data center engineering](https://build.inc/learn/ai-engineering/data-centers) page covers how the utility connection shapes the design, and the [data center site selection guide](https://build.inc/learn/ai-site-selection/data-centers) covers how we screen for it.

## How Build helps

Build is a vertically integrated development firm. With our own technology stack, our team finds sites, validates the power path against utility and grid operator rules, and takes the sites that pass to shovel-ready. For a client, that means knowing which service, capacity and cost rules apply to a site before capital is committed. See [Build's site selection service](https://build.inc/services/site-selection).

## Key takeaways

-   Six grid operators filed large-load reforms at FERC from 13 to 20 November 2026: ISO-NE, CAISO, MISO, NYISO, PJM and SPP.

-   POWER reports they generally use 50 MW to identify a large load, but service terms differ widely.

-   Four propose price-based curtailment for non-firm service, with triggers from $25/MWh (SPP) to $250/MWh (ISO-NE).

-   Capacity and cost rules vary, from bring-your-own-capacity in ISO-NE to SPP's $500,000/MW funding cap.

-   The proposals are not final and mostly take effect from 2027 or later.

## Sources

-   [POWER: Six Grid Operators Respond to FERC With Distinct Plans for Large-Load Integration](https://www.powermag.com/five-grid-operators-respond-to-ferc-with-distinct-plans-for-large-load-integration/), 19 November 2026, updated 23 November 2026

-   [FERC: Interconnection of Large Loads to the Interstate Transmission System, Docket RM26-4-000](https://www.ferc.gov/rm26-4)

## Frequently Asked Questions:

Which grid operators filed large-load plans with FERC in November 2026?

Six: ISO New England on 13 November; CAISO, MISO, NYISO and PJM (with PJM's transmission owners) on 16 November; and Southwest Power Pool on 20 November.

Why did the grid operators file?

They were responding to show-cause orders FERC issued on 18 June 2026, which found existing regional tariffs may be unjust and unreasonable in how they treat large loads such as data centers.

Do all grid operators use a 50 MW large-load threshold?

POWER reports they generally use 50 MW to identify large loads. Specific rules vary, and other thresholds appear, such as MISO's 200 MW study for loads partnered with a generator. Check each tariff.

What is non-firm service for a data center?

Grid service that can be curtailed, for example when wholesale prices pass a set level. It may let a project energize before all upgrades for firm service are built.

Will data centers have to bring their own generation?

In some regions. ISO-NE proposes that firm service require new capacity designated by the customer, while SPP's non-firm PALS service carries no extra resource adequacy obligation.

When do the changes take effect?

Requested dates mostly fall between February 2027 and 2029, and all depend on FERC approval.

How does Build help developers with these rules?

Build is a vertically integrated development firm. Our team validates each site's power path against the applicable utility and grid operator rules and takes the sites that pass to shovel-ready.

[Industry ### Spain's Data Center Decree: What Developers Must Prove November 24, 2026](https://build.inc/insights/spain-data-center-decree-what-developers-must-prove)[Industry ### What Is Hourly Matching for Data Center Power? November 24, 2026](https://build.inc/insights/what-is-hourly-matching-data-center-power)[Industry ### What Is a Large Load? The Emerging 50 MW Threshold Explained November 23, 2026](https://build.inc/insights/what-is-a-large-load)
