# OpenAI's Georgia Campus Approval: What Got It Through

Effingham County approved the site plan for OpenAI's roughly 1,400-acre Project Camellia on 17 November. Existing industrial zoning, settled power and direct answers to commissioners carried it; a federal wetlands permit is still needed.

by Build Team • November 20, 2026 • 6 min read

**Short answer:** On 17 November, Effingham County, Georgia, commissioners unanimously approved the site plan for OpenAI's Project Camellia, a data center campus of roughly 1,400 acres at the Savannah Gateway Industrial Hub, with the chairman recused ([Effingham Herald](https://www.effinghamherald.net/data-centers/effingham-approves-openai-site-plan-tables-moratorium-project-camellia-data-center-georgia/)). Three things got it through: the site sat in an industrial park where the use met existing zoning, the power supplier was settled, and the team answered commissioners' questions on buildings, buffers and noise after the vote was tabled two weeks earlier. The approval does not allow construction yet; county agreements and a federal wetlands permit are still needed. For developers, it shows how [data center planning and permitting](https://build.inc/learn/ai-planning-permitting/data-centers) is won: validate the zoning path and power early, and answer community concerns in the site plan itself.

## What was approved?

According to the Effingham Herald and WTOC:

Item

Detail

Project

Project Camellia, about 1,400 acres within the roughly 2,700-acre Savannah Gateway Industrial Hub

Vote

Site plan approved unanimously on 17 November by the five participating commissioners; the chairman, a Southern Company employee, recused himself because Georgia Power will supply the project

Buildings

Six data center buildings instead of four, after one building of about 1 million square feet was split into two of about 471,000 square feet each

Other site elements

A warehouse, an operations building, two substations and cooling infrastructure

Community measures

A 20-foot berm along Hodgeville Road, a 300-foot vegetative buffer and a noise study under way (WTOC)

Still needed

Development agreement, water and sewer agreement, land disturbance approval, development plan and building review, and a federal wetlands permit

## What got it through?

**1\. The zoning path was already open.** The Atlanta Journal-Constitution reported that the facility met current zoning standards and was not subject to a separate zoning review ([AJC](https://www.ajc.com/news/2026/11/openai-data-center-fight-georgia/)). That is the advantage of an industrial-zoned site. See [by-right zoning vs special use permits](https://build.inc/insights/data-center-by-right-zoning-vs-special-use-permit).

**2\. Power was settled.** Georgia Power will supply the project, and WTOC reported the project's power agreement remained unchanged. Commissioners were not asked to approve a site with an open power question.

**3\. Questions were answered, not deferred.** The vote was tabled on 3 November. At the next meeting the project engineer explained the move to six buildings, which he said would improve access for first responders and allow faster construction without more power or water use.

**4\. The plan addressed visible impacts.** The berm, buffer and noise study answered concerns residents raise at nearly every data center hearing.

## What is still open?

Two items show that site plan approval is a milestone, not the finish line:

-   **Federal wetlands permit.** OpenAI filed a Section 404 application on 5 October to fill about 72 acres of forested wetlands, and the comment period was extended to 3 December, the Herald reported. Work requiring federal authorization in those wetlands cannot start until the U.S. Army Corps of Engineers issues the permit. Our guide to [floodplain and wetlands screening](https://build.inc/insights/data-center-floodplain-wetlands-screening) covers how to spot this early.

-   **The rules for the next project are changing.** Commissioners postponed a proposed moratorium on future data centers to January, and held a first reading of an amendment that would make data centers a conditional use requiring public zoning review. Project Camellia would be excluded from the moratorium as proposed.

## What should developers take from it?

-   **Validate the zoning path before land spend.** By-right sites move faster, but windows close. See [2026 data center moratoriums](https://build.inc/insights/data-center-moratoriums-2026).

-   **Settle power before the hearing.** A clear supplier and agreement removes the largest open question.

-   **Screen wetlands at site selection.** A federal permit can sit on the critical path even after local approval.

-   **Put mitigation in the first site plan.** Buffers, berms, noise studies and water strategy are approval tools.

## What does Build do?

Build is the development execution engine for infrastructure and data centers, built for quality and speed. We source sites, validate zoning, power, wetlands and water against primary sources, then bundle the planning, permitting and design services that turn a passing site into an approvable plan. Start with [data center site selection](https://build.inc/learn/ai-site-selection/data-centers) or read how we work in [AI native development](https://build.inc/learn/ai-native-development).

## Key takeaways

-   Effingham County approved the Project Camellia site plan on 17 November; construction still needs county agreements and a federal wetlands permit.

-   Existing industrial zoning, a settled power supplier and direct answers to commissioners carried the vote.

-   The county is now considering a moratorium and conditional-use rules, so the next project may face a harder path.

## Sources

-   [Effingham Herald: Effingham approves OpenAI site plan, tables moratorium (17 Nov 2026)](https://www.effinghamherald.net/data-centers/effingham-approves-openai-site-plan-tables-moratorium-project-camellia-data-center-georgia/)

-   [WTOC: Effingham County approves OpenAI data center site plan (17 Nov 2026)](https://www.wtoc.com/2026/11/18/effingham-county-commissioners-vote-approve-project-camellia-site-plan/)

-   [Atlanta Journal-Constitution: Site plan for giant OpenAI data center approved on Georgia coast](https://www.ajc.com/news/2026/11/openai-data-center-fight-georgia/)

## Frequently Asked Questions:

What did Effingham County approve?

On 17 November commissioners unanimously approved the site plan for OpenAI's Project Camellia, about 1,400 acres at the Savannah Gateway Industrial Hub, with the chairman recused.

Can construction start now?

Not fully. The project still needs a development agreement, water and sewer terms, land disturbance and building approvals, and a federal wetlands permit.

Why did the plan not need rezoning?

The Atlanta Journal-Constitution reported that the facility met current zoning standards and was not subject to a separate zoning review.

What is the wetlands permit?

A Section 404 permit from the U.S. Army Corps of Engineers. OpenAI applied to fill about 72 acres of forested wetlands, with public comment open until 3 December.

Is Effingham County changing its rules?

Commissioners postponed a proposed moratorium on future data centers to January and held a first reading of a rule that would make data centers a conditional use.

What is the lesson for developers?

Validate the zoning path, power supply and wetlands early, and put community mitigation into the first site plan.

[Markets ### Salt Lake City's Data Center Pause: What to Check November 19, 2026](https://build.inc/insights/salt-lake-city-data-center-pause-what-to-check)[Markets ### Texas Resumes Data Center Permits: What to Do Now November 18, 2026](https://build.inc/insights/texas-resumes-data-center-permits)[Markets ### Neocloud vs Colocation: Who Builds and What Sites Need November 17, 2026](https://build.inc/insights/neocloud-vs-colocation-data-center-sites)