---
title: "Georgia's 100 MW Data Center Rule: What Developers Need to Know | Insights | Build"
description: "Georgia's 100 MW data center rule is a Public Service Commission rule for Georgia Power, approved in January 2025. It allows 5 to 15 year contracts, minimum billing and upstream cost responsibility for new customers above 100 MW, and new contracts go to the PSC for review. It is not a new state statute."
url: https://build.inc/insights/georgia-100-mw-data-center-rule
---

[Markets](https://build.inc/insights?category=markets)

# Georgia's 100 MW Data Center Rule: What Developers Need to Know

Georgia's 100 MW data center rule is a Public Service Commission rule for Georgia Power, approved in January 2025. It allows 5 to 15 year contracts, minimum billing and upstream cost responsibility for new customers above 100 MW, and new contracts go to the PSC for review. It is not a new state statute.

by Build Team • November 23, 2026 • 5 min read

**Short answer:** Georgia's 100 MW rule is a Public Service Commission (PSC) rule for Georgia Power, not a new state statute. Approved in January 2025, it lets Georgia Power set special terms for any new customer using more than 100 MW: longer contracts, minimum bills, and a share of upstream grid costs. Each new 100 MW contract goes to the PSC for review. Developers do not file a state form. They negotiate a contract that the PSC then reviews, so the work that matters happens before the utility conversation starts.

## What is Georgia's 100 MW data center rule?

In January 2025 the [Georgia PSC voted unanimously](https://psc.ga.gov/site/assets/files/8617/media_advisory_data_centers_rule_1-23-2025.pdf) to approve a Georgia Power rule for new customers using more than 100 megawatts. The rule allows terms and conditions beyond those used for standard customers, to address the risks of very large loads. Georgia law requires the PSC to approve all new or amended Georgia Power rules.

Item

What the PSC says

Who it covers

New customers using more than 100 MW

Contract length

Longer terms allowed, from 5-year up to 15-year contracts

Billing

Minimum billing requirements allowed

Costs

Site-specific costs plus upstream generation, transmission and distribution costs, as construction progresses

Oversight

New contracts in the 100 MW category are submitted to the PSC for review

Source: [PSC news release, 23 January 2025](https://psc.ga.gov/site/assets/files/8617/media_advisory_data_centers_rule_1-23-2025.pdf).

## What do developers actually file?

Not much, directly. The rule governs what Georgia Power can put in a contract and what it must hand the PSC. The PSC's [data center fact sheet](https://psc.ga.gov/site/downloads/datacenterfactsheet_202609.pdf) (September 2026) says Georgia Power must give the PSC all new data center contracts at least 30 days before execution.

For a developer, that means three practical things:

-   **Expect contract terms, not a form.** Term length, minimum billing and cost responsibility are negotiated with the utility, then reviewed by the PSC.

-   **Expect the PSC to see your numbers.** The PSC publishes public summaries of reviewed contracts. The September 2026 fact sheet links to one for a 3,200 MW contract that staff reviewed on 26 August 2026.

-   **Expect to carry cost.** The stated purpose is to make sure large new users keep paying for infrastructure built for them, even if they later leave the state.

## Did Georgia pass a new data center law in 2026?

Not as of the most recent reporting we could verify. [Georgia Recorder reported in April 2026](https://georgiarecorder.com/2026/04/10/data-center-pfas-bills-were-a-bust-but-georgia-environmentalists-cheer-boost-for-conservation/) that lawmakers failed to finalize any of the data center bills before the 2026 session ended, including one that would have written existing PSC regulations into law. So the 100 MW rule remains a PSC rule. If you see a claim that a new statute sets a 100 MW filing requirement, check it against the General Assembly record before you rely on it.

## How big is the load behind the rule?

Large. The PSC fact sheet says Georgia Power's generation need estimate rose from 400 MW in 2022 to 6,600 MW in 2023 and 8,500 MW two years later, against about 22,000 MW currently deployed statewide. On 19 December 2025 the PSC approved certification of 9,985 MW of new generation, and the PSC says about 80 percent of it is expected to serve data centers. By September 2026 the PSC says Georgia Power had secured customers for all 9,985 MW.

That context explains the rule's design. A utility that is building generation for data centers wants the customers to be committed before the steel goes in the ground.

## What does the rule mean for a project schedule?

The rule does not add a state permit, but it does shape the order of work. A 100 MW project in Georgia should plan for these steps:

1.  **Confirm the load size early.** The rule applies above 100 MW, so a staged build that crosses the line at phase two still needs a plan for it.

2.  **Price the contract terms.** Minimum bills and a multi-year term change the cost of capital, and they should sit in the underwriting before land is committed.

3.  **Map the local approvals.** Zoning, water and local permits still run through counties and cities. The [OpenAI Georgia campus approval](https://build.inc/insights/openai-georgia-campus-approval-what-got-it-through) shows what a project needed to clear locally.

4.  **Line up the utility and PSC timeline.** The 30-day contract review window sits inside the schedule, not after it.

For the wider approvals picture, see our [planning and permitting guide for data centers](https://build.inc/learn/ai-planning-permitting/data-centers).

## What does Georgia's rule not do?

-   It does not cap data center construction or ban projects.

-   The PSC's description of the rule does not set a fixed minimum-bill amount or a published per-MW charge.

-   It does not replace local zoning, water or air permits.

## What Build does here

Build is a vertically integrated development firm. With our own technology stack, we take a data center project from site to shovel-ready: power path, approvals map and procurement plan. For a Georgia project, the client gets the utility contract terms and local approval path laid out before they commit capital.

## Key takeaways

-   The 100 MW rule is a Georgia PSC rule for Georgia Power, approved in January 2025.

-   It allows 5 to 15 year contracts, minimum billing and upstream cost responsibility for new customers above 100 MW.

-   Georgia Power must give the PSC new data center contracts at least 30 days before execution.

-   Georgia Recorder reported in April 2026 that no data center bill passed that session.

## Sources

-   [Georgia PSC news release on the large-load rule](https://psc.ga.gov/site/assets/files/8617/media_advisory_data_centers_rule_1-23-2025.pdf), 23 January 2025

-   [Georgia PSC data center fact sheet](https://psc.ga.gov/site/downloads/datacenterfactsheet_202609.pdf), September 2026

-   [Georgia Recorder, 2026 session wrap-up on data center bills](https://georgiarecorder.com/2026/04/10/data-center-pfas-bills-were-a-bust-but-georgia-environmentalists-cheer-boost-for-conservation/), 10 April 2026

## Frequently Asked Questions:

What is Georgia's 100 MW data center rule?

It is a Georgia Public Service Commission rule, approved in January 2025, that lets Georgia Power set special terms for new customers using more than 100 MW. Terms can include contracts of 5 to 15 years, minimum billing and responsibility for upstream grid costs.

What do data center developers have to file in Georgia?

Developers do not file a dedicated state form under the rule. Georgia Power negotiates the contract and, according to the PSC's September 2026 fact sheet, gives new data center contracts to the PSC at least 30 days before execution.

Is the 100 MW rule a state law?

No. It is a PSC-approved Georgia Power rule. Georgia Recorder reported in April 2026 that the legislature did not finalize any data center bills in the 2026 session.

Does the rule limit how many data centers Georgia can build?

No. It sets contract and cost terms for very large new customers. It does not cap construction or replace local zoning, water or air permits.

What does the rule mean for a project just under 100 MW?

The special large-load terms apply above 100 MW. A project planned in phases should check whether total planned demand crosses that line.

[Markets ### TVA's Data Center Rate Class: About $1.5M per MW Explained November 23, 2026](https://build.inc/insights/tva-data-center-capacity-commitment-charge)[Markets ### OpenAI's Georgia Campus Approval: What Got It Through November 20, 2026](https://build.inc/insights/openai-georgia-campus-approval-what-got-it-through)[Markets ### Salt Lake City's Data Center Pause: What to Check November 19, 2026](https://build.inc/insights/salt-lake-city-data-center-pause-what-to-check)
